An example of a tool SCIRT has used to communicate its projects to a community.
A presentation given at the New Zealand Geospatial Research Conference 2015.
A plan which outlines the function, roles and responsibilities of SCIRT during an emergency event affecting SCIRT construction works. The first version of this plan was produced on 30 April 2012. Note that personal details of key personnel have been removed from this document.
A plan which aims to ensure an environment of Zero Harm on SCIRT worksites. The first version of this plan was produced on 29 July 2011.
A document which describes SCIRT's experience with the trenchless technology of pipe lining.
This document contains a list of the roles of people that have requested access to the SCIRT GIS viewer.
A design guideline which provides guidance to project definition and design teams on how to use Pipe Damage Assessment Tool (PDAT) outputs in their scoping and concept design work.
A document providing an overview of the SCIRT Communication Team, including its purpose, objectives and decision-making processes.
A document that outlines objectives and ways of working collaboratively, which team members signed to show their commitment.
An advertisement from April 2016 informing residents that local businesses are still open, despite detours and roadworks.
A tool, in the form of a poster, given to workshop and toolbox participants and hung up at worksites and in offices, outlining five easy steps to minimise the impact of roadworks on businesses.
A plan which outlines how to manage the environmental impacts that result from SCIRT works. The first version of this plan was produced on 20 July 2011.
A document containing examples of items provided in a folder for businesses. These are taken to the initial face-to-face meeting with business owners to discuss the impact and disruption of upcoming SCIRT rebuild works.
A plan which outlines how projects will be estimated to generate project Target Out-turn Costs (TOCs), and how these link into the programme TOC. The first version of this plan was produced on 29 July 2011.
A runsheet created for the SCIRT and New Zealand Red Cross humaneers action learning group.
A run sheet which details who will do what at the opening of the Gloucester Street bridge.
A flowchart which illustrates where the G-File was used throughout the life cycle of asset data collection, processing and delivery.
A report which details the financial and societal value that the SCIRT Training Centre created.
Photograph captioned by BeckerFraserPhotos, "The conical top of the tower at the Arts Centre was removed and secured after the September earthquake".
A photograph captioned by BeckerFraserPhotos, "The PricewaterhouseCoopers, Building, Forsyth Barr Building, and the Copthorne Hotel viewed from Cambridge Terrace".
Photograph captioned by BeckerFraserPhotos, "Otakaro Place, Bexley. Look at the slope of the garage, and the cracks in the drive".
Photograph captioned by BeckerFraserPhotos, "Otakaro Place, Bexley. A great hole has opened up between the deck and the garden with fissures all over the garden".
Photograph captioned by BeckerFraserPhotos, "Otakaro Place, Bexley. Look at the difference in the vertical line in the edge of the building".
A photograph of temporary street furniture outside the temporary Central Library on Tuam Street. The furniture was designed and fabricated by F3 Design for the Christchurch City Council.
The roof of a tram stop resting on blocks on the lawn outside the Arts Centre. In front is a bust of Sir Miles Warren, a prominent Christchurch architect.
A photograph of campervans parked in Hagley Park. These were used as temporary accommodation for many emergency management personnel who travelled to Christchurch after the 22 February 2011 earthquake.
A photograph of a volunteer from the Wellington Emergency Management Office ordering at a temporary café. The café was set up in a house in the Christchurch central city.
A photograph of a volunteer from the Wellington Emergency Management Office ordering at a temporary café. The café was set up in a house in the Christchurch central city.
A photograph of a hallway in a building in the Christchurch city centre. Concrete blocks and other rubble fill the stairwell on the left-hand side of the hallway.
A photograph of campervans parked in Hagley Park. These were used as temporary accommodation for many emergency management personnel who travelled to Christchurch after the 22 February 2011 earthquake.